1. Magnitudes of the plan
The following table summarises the main variations between the information reported at 6M26 and 9M26.
It is worth noting that in 9M26 two new metrics appear that were not shown in 6M26. The cost per MW is an average of 10.9 million euros: 9.6 in Phase I, 10.8 in Phase II and 11.1 in Phase III. The GRI (gross rental income) is an average of 133 euros/kW/month: 126, 132 and 135 respectively. According to our estimates, the cost per MW of Phase III rises from about 10.9 million euros to 11.1 million euros, with an investment that decreases by -2.4% and capacity that decreases by -4.9%. Additionally, the management team has updated the underwriting rents by +2 euros/kW/month in Phase II and by +2 euros/kW/month in Phase III, although it indicates that it is signing above those levels. In Phase II, this corresponds to about 6 million euros of GRI (254 MW x 2 euros x 12 months), which is the increase in GRI from 397 million euros to 403 million euros in the previous table.
2. What is behind the -20 MW of Phase III. The change is a restructuring. 162 MW are exiting and 142 MW are entering:
• Exiting: BIO-ARA 04-05 and the repowering of BIO-ARA 01 (162 MW). They had the granted power, but they are still pending electrical infrastructure and there are administrative delays. They move to the future projects portfolio. The generating partner (Solaria) has lost its electrical licenses due to a conflict with the Basque Government, so MERLIN is exploring an alternative location with greater self-consumption potential or supply from the grid, which would be subject to the Royal Decree and would be difficult to cover with PPA (150 MW). These projects accounted for 85% of the MW that could be deemed NOT VIABLE according to the criteria of additionality and hourly correlation under the current wording of the Royal Decree on data centres.
• Entering:
1. ZGZ-MAGA 01, 96 MW, new project. It has high levels of self-consumption, similar to WIND. Additionally, a Declaration of General Interest of Aragon has been requested.
2. EXT-NAV 01 (Navalmoral), 20 MW. The license is expected by the end of November and the structure for 100 MW will be built, equipping 20. An optionality of up to 1.4 GW IT is mentioned.
3. Repowering of LIS-VFX 03-04-05: +20 MW, in advanced rental negotiations.
4. Repowering of MAD-GET 01: +6 MW, also in advanced negotiations. This changes the geographical profile: Bilbao remains at 118 MW, Zaragoza rises to 240 MW (WIND and MAGA) and Extremadura appears with 20 MW. The MERLIN press release justifies the exit from Bilbao due to electrical delays.
3. Changes in dates and status, by project.
Phase I (64 MW)
• At 6M26 only 50 MW were equipped. Now all 64 MW are equipped and rented.
• MAD-GET 01 changes from "generating income when the electrical connection works are completed (4Q26)" to “starting to generate cash in November 2026”
• The repowering of BCN-PLZF 01 was delivered in July and is now fully operational.
• The report for 6M26 indicated gross rents for Phase I of 68 million euros for 2026. The 9M26 report only mentions the 97 million euros for 2027.
Phase II (254 MW)
• BIO-ARA 02 (48 MW): no changes. It is 100% rented, to be delivered in December 2026, with cash of 20 MW in January 2027 and 28 MW in June 2027.
• BIO-ARA 01 (48 MW): no changes. It is 100% rented and will be delivered in December 2027.
• LIS-VFX 01-02 (80 MW): in 6M26 no date was given. Now the delivery is specified for December 2027. It remains in advanced rental negotiations.
• MAD-GET 02 (48 MW): the demolition works change from "in progress, completion in 2026" to "close to completion". The license is still expected for 1Q27 and the project remains reserved.
• MAD-TCS 01 (30 MW): changes from "planning completed" to license requested, expected for 1Q27. Now there are 20 MW reserved, which is new.
• The commercial tone is strengthened: from "beating forecasts" to "well exceeding internal forecasts".
Phase III (386 MW)
• LIS-VFX 03-04-05: the commissioning remains in 1S29. This is the only aspect that remains the same, in addition to the addition of the +20 MW of repowering.
• ZGZ-WIND (144 MW): the start of construction remains in 3Q27 and commissioning in 2S29. This is maintained.
• Phase III stabilises in 2031 instead of 2032, according to the new table. The management team states that there would be no cash delays even in the worst regulatory scenario, and that it expects to exceed 1,000 million euros of gross rents in 2029 and 1,500 million euros in 2031.
4. New commercial and financial indicators
• Marketing: 9M26 quantifies for the first time the commercial status of the MEGA Plan. There are 160 MW rented (64 from Phase I plus 48 from BIO-ARA 02 and 48 from BIO-ARA 01), 206 MW in advanced negotiations and 68 MW reserved (MAD-GET 02 and 20 MW from MAD-TCS). The 206 MW correspond to LIS-VFX 01-02 (80), LIS-VFX 03-04-05 (100), +20 MW of repowering in Lisbon and +6 MW in Getafe.
• Gross rents from data centres: 28.1 million euros at 6M26 and 46.5 million euros at 9M26, which implies about 18.4 million euros in 3T26. At 9M25 it was 19.1 million euros.
• Valuation: there is no new appraisal in the quarter. The current data is from 6M26: 988 million euros of GAV in operational data centres (gross yield 6.2%) and 1,115 million euros in WIP and land. • Investment: in 9M26 acquisitions total 44.0 million euros (land in Navalmoral, Tres Cantos and Getafe II) compared to 26.2 million euros in 6M26. Greenfield developments total 526.4 million euros, compared to 367.9 million euros at 6M26. This item mixes logistics and data centres.
• Financing: the financing status does not change. Phases I and II are fully financed and Phase III only partially.
5. Impact of batteries (BESS) on investment and YoC.
For now, the Royal Decree maintains the obligation to cover 80% of consumption with additional renewables with hourly correlation. MERLIN has quantified a "worst-case scenario" in which the Decree is approved, remains in force, and neither the precautionary measures before the Supreme Court nor the intervention of the EU succeed. To comply, it has calculated the necessary battery (BESS) and photovoltaic capacity in the affected projects: 338 MW IT, 48% of the plan (BIO-ARA 01, 48 MW; MAD-TCS 01, 30 MW; ZGZ-WIND 01, 144 MW; ZGZ-MAGA 01, 96 MW; EXT-NAV 01, 20 MW). In Zaragoza, with annual correlation, the 80% would be easily exceeded, but the hourly requirement forces investment in batteries. The company claims that with this capex the 704 MW would comply with the decree and has opted to meet the 80% from the outset, without taking advantage of the transitional period, which would require adherence to the SRAP disconnection system without compensation.
The additional capex in BESS would be 863 million euros (11.3% of the investment of 7,671 million euros; 1.2 million euros per MW over the total of the plan). MERLIN expects to "prudently" recover about 35% (310 million euros) through battery arbitrage and/or energy sales, so the non-recoverable cost would be 553 million euros (7.2%; 0.78 million euros per MW). In individual projects, the cost overrun would be 20%-30% according to the management team. Table 2 shows the effect on investment and the gross YoC of the plan.
Impact reading:
• Company scenario: the investment of the plan rises by +7.2% to 8,224 million euros and the gross YoC would drop from 14.7% to 13.7% (-1.0 p.p.). Without any recovery, the investment rises by +11.3% to 8,534 million euros and the YoC drops to 13.2% (-1.5 p.p.). Both calculations assume that the GRI does not change.
• Affected perimeter: the effect concentrates on 5 projects. According to our estimates, their YoC would drop from approximately 14.6% to approximately 12.7% in the company scenario and to approximately 11.9% without recovery, consistent with the cost overrun of 20%-30% per project mentioned by the management team. Nevertheless, it would still be more than 8 p.p. above the estimated average cost of debt for 2030 (3.8%).
• Recovery depends on energy prices: the 310 million euros recoverable would come from battery arbitrage and sales of surpluses, that is, from non-contractual revenues. The company qualifies them as prudent, but does not detail the price hypotheses or what return they provide beyond returning the capital.
• Per share: on 620 million shares, the 553 million euros equate to approximately 0.89 euros/share (5.1% of our P.O.) and the 863 million euros to approximately 1.39 euros/share (7.9%). These are nominal amounts without discounting: the capex would be spread until 2031 and the company has financed 100% of Phase II and 25% of Phase III.
• Appraisals: management does not expect a significant impact on asset value, as appraisers would apply the market yield (approximately 6%) to a return that would drop from approximately 14.5% to approximately 13.5%. The next appraisal is the year-end one.
• Battery useful life: MERLIN amortises them over 10 years and purchases capacity for 12 minutes because it expects it to drop to 9 minutes in year 7. The company does not clarify whether the 863 million euros include replacement, and estimates a residual value of 20%-40%.
• Timeline and asymmetry: management expects the Decree to be approved in the Council of Ministers on 17, 20 or 24 November, with entry into force in mid-December; Parliament will be constituted on 23 December and a new government could form in early January. If the decree is repealed or stalled (Supreme Court, EU), the additional capex would disappear, so the company presents it as a scenario that "can only improve".
6. Valuation
We believe that the restructuring of the project portfolio of the MEGA PLAN should have a positive impact on the share price, as the regulatory uncertainty from the new Royal Decree on data centres that could affect the viability of 26.5% of the total capacity projected by MERLIN is reduced to approximately 4% according to our estimates. Likewise, we value positively the proactivity of the management team in adapting its projects to regulatory changes, as well as the flexibility of the portfolio. However, 338 MW (48% of the plan) would have to incorporate batteries to comply with hourly correlation (point 5): exposure to the Decree shifts from viability risk to cost and profitability risk.
As a negative point, we highlight the loss of profitability on cost of approximately -1 p.p. (from 14.7% to 13.7%) in the company scenario, which contemplates recovering 35% of the capex in batteries through arbitrage or energy sales. Without that recovery, the drop in profitability would be up to -1.5 p.p. This stems from the 863 million euros of additional investment in BESS (11.3% of the investment of the plan) in the 338 affected MW. Let us remember that this scenario would only materialise if the Royal Decree is approved and remains in force and, in that case, would eliminate regulatory uncertainty.